In early September 2018, construction work began on the rough route of the track in the upper part (middle station of Gaislachkogl mountain gondola - Stiegele). About two thirds were already completed by the end of November. "We startet with the completion of the track at the beginning of May 2019. In terms of earthworks, the last section of the route was on the program. It was also very important to install crash protection systems throughout the upper section, as well as cable trenches and lighting pylons," explains Lukas Arnold, Project Manager at Bergbahnen Sölden.